Check out our JULY 2010 Delivery statistics:
Mechanical Seals
98.4% on-time delivery for Standard Products (target = 96%)
93.7% on-time delivery for Standard Plus Products (target = 93%)
Bearing Isolators
97.8% on-time delivery for Magtecta Products (target = 95.5%)
99.6% on-time delivery for Labtecta Products (target = 95.5%)
Lead Time
| Standard Labtecta Month of JULY 2010 |
| Number of working days |
1 day |
3 day |
7 day |
14 day |
21 day |
28 day |
28 day+ |
| Percentage |
54% |
72% |
93% |
98% |
100% |
100% |
100% |
Quick delivery of Labtecta Bearing Isolators is seen as a priority by many of our customers.
AESSEAL has the capacity and capability to despatch all Standard Labtecta Bearing Isolators within 24 hours.
However, many customers request specified delivery dates some time in the future. AESSEAL met these promised dates on 99.6% of occasions in July.
|