Case Studies

curve-down
Displaying 1 - 7 of 10
AU flag

Case Studies

A coal mine in Australia was having seal failures roughly every two weeks on two disposal pumps.

AU flag

Case Studies

The installation of a new type of seal was the remedy for a series of seal failures at an Australian mining company.

AU flag

Case Studies

An iron ore mine in Australia was experiencing unacceptably high maintenance costs on its Warman Thickener Underflow pumps. The pumps were sealed with Gland Packing that was flushed with 48litres per minute.

Case study front cover
AU flag

Case Studies

A local municipal swimming pool in Australia was using gland packing on the main pool pump.

Case Study Front Page
AU flag

Case Studies

Ongoing reliability issues with their pulp agitator mechanical seals led Australian pulp and paper manufacturer to turn to AESSEAL® for assistance.

Case Study Front Cover
AU flag

Case Studies

A mean time between failure (MTBF) of just 2 months meant that costs at over $135,000 AUD for pump maintenance were unacceptably high.

AU flag

Case Studies

A coal mine in Australia was using gland packing on 3 coal slurry transfer pumps.