Case Ref
CH00704 - CH00706
Country
Australia

Summary

A coal mine in Australia was using gland packing on 3 coal slurry transfer pumps. The gland packing would start to fail after 6 weeks and the yearly maintenance bill for the 3 pumps was over $135,000AUD.

More Industry Related Content

Related Products Pages

Heavy Duty Slurry Seals
Water Management Systems

Related Case Studies

LabTecta ends contamination problem at Australian mining company
Huge cost savings and improved reliability with gland packing upgrade
Improved safety and production efficiency while reducing water consumption
AESSEAL cuts water usage by 75 percent at US company
Replacing lip seals reduces cost, improves reliability and saves the environment
ZAR84,000 Saving with reliability upgrade from packing
Five times improvement in reliability
Reduced Water Consumption Quickly Repays Investment