Case Ref
CH00704 - CH00706
Country
Australia

A coal mine in Australia was using gland packing on 3 coal slurry transfer pumps. The gland packing would start to fail after 6 weeks and the yearly maintenance bill for the 3 pumps was over $135,000AUD.